logo_adjudicatetoday

Government has recognised that prompt payment on account is vital to the stability and efficiency of the building and construction industry.  Too often the party liable to pay for construction work or related goods or services (the respondent), has manufactured a dispute to deny, or try to delay, payment.  In other situations, respondents have tried to string out the time for payment with promises of future work if only the claimant just waited a bit longer.

The objective of the Building and Construction Industry Payments Act 2004 (often called the Security of Payment Act) is to ensure that any party that contracts to carry out construction work, or supply related goods or services, on projects for the private and public sectors in Queensland is entitled to promptly receive and recover all progress payments that are due, including final payments and retention monies.

The Act creates a dispute resolution process (adjudication) that allows parties alleging they are owed monies under a construction contract (the claimant) to promptly obtain payment on an interim basis, based on an assessment of the merits of the claim by an appropriately qualified and independent adjudicator.

The Act also permits claimants access to compulsory rapid adjudication when the construction contract has no provision for progress payments and/or the contract is for a single supply at a fixed price.

To take advantage of the Act, a claimant must ensure that a payment claim includes the notice: This is a payment claim made under the Building and Construction Industry Payments Act 2004 Qld or words to that effect.  Where the notice has not been included and the claimant wishes to benefit from the rights created by the Act, a payment claim with the notice included must be submitted in accordance with the timeframes of the Act.

The adjudication process is not only rapid (the adjudicator must make the decision within 10 business days unless the parties agree to extend the time) but if the respondent’s reasons for not paying are spurious, the respondent is generally liable for all adjudication fees and interest.  The process is usually entirely in writing and is so simple that, for most claims, a lawyer should not be necessary.  After adjudication, the claimant may obtain an adjudication certificate for lodgment at the appropriate court which registers it as a judgment debt.

Unlike litigation or arbitration, compulsory rapid adjudication cannot result in the claimant being liable to the respondent. The respondent cannot initiate adjudication or obtain a determination that the claimant must pay the respondent money. The maximum liability of the unsuccessful claimant is the amount of the adjudication fees.  Even then, the fees are shared equally by the parties unless the adjudicator construction_worker_timberdetermines otherwise.

Construction work and the supply of related goods and services includes:

  • building work;
  • civil engineering;
  • demolition;
  • electrical;
  • hire of plant or equipment;
  • landscaping;
  • maintenance;
  • professional services such as architectural design, surveying and soil testing;
  • supply of building materials.

The Act broadly defines those persons who may make progress claims under the Act, including:

  • contractors against clients (eg. principals, developers, owner-builders);
  • subcontractors against contractors;
  • suppliers of building components against purchasers;
  • architects, engineers, and others (eg. consultants) providing advice against clients;
  • plant and equipment hirers against clients.

The Act does not apply to:

  • Homeowners (refer to 'resident owner' as defined under the Domestic Building Contracts Act 2000) if the homeowner is party to the contract, to the extent the contract relates to a building or part of a building where the homeowner resides or intends to reside. Note that a person who holds (or should hold) an owner-builder's permit under the Queensland Building Services Authority Act 1991 is not by definition a resident-owner and therefore is covered by the Act.

  • A construction contract between parties to the extent it deals with construction work carried on outside Queensland or related goods and services supplied for construction work carried on outside Queensland.

  • A construction contract between parties to the extent that it forms part of a loan agreement, a contract of guarantee or a contract of insurance under which a recognised financial institution undertakes to lend or repay an amount lent; guarantee payment of an amount owing or repayment of an amount lent; or provide an indemnity relating to construction work carried out or related goods and services supplied.

  • Contracts in which the consideration payable for construction work carried out or related goods and services supplied under the contract, is calculated other than by reference to the value of the work or goods and services supplied.

    carpenter with yellow helmetThe Act ensures that the party providing work, goods or services can force the respondent to make payment on account. 

    When an adjudicator has determined the amount due, the Act provides an expedited means of obtaining a court judgment for payment of the amount due.  The claimant only has to obtain an Adjudication Certificate from Adjudicate Today and lodge that with a court, together with an affidavit of the amount still unpaid.  Judgment is granted automatically by the court, that is, without the need for a summons or a hearing.

If the process has been carried out in accordance with the Act, the respondent cannot challenge the adjudicator’s determination in court.  Adjudication is an expedited determination based on unsworn submissions, not a determination based upon sworn testimony.  The respondent who is dissatisfied with the adjudicator's decision has the option of suing separately for repayment of any alleged overpayment.

The Act includes other protections for claimants such as a right to suspend work and be paid for any losses and expenses if sacked because of the suspension.  Respondents cannot claim or sue for liquidated damages because of a suspension of work under the Act.  The Act bars “pay when paid” and/or “paid if paid” clauses and overturns them even if they are included in the contract.  All forms of contracts are covered - written and oral.  It also provides a minimum rate of interest on late progress payments.  The claimant and the respondent share equally the fees payable to Adjudicate Today and the adjudicator, unless the adjudicator decides otherwise. Generally adjudicators award all fees against respondents if the claimant has been successful in the adjudication application.


Website designed and developed by Langoor.